The number in this month's headlines is 3,000. WDRB and WAVE reported that Clore Station will bring about 3,000 homes and apartments to Crestwood, along with a hospital, an arts center, a grocery store and senior living, in a $2.5 billion project along Interstate 71. For a buyer deciding in the next few years, the number that matters is smaller. The first phase covers 25 acres and 160 residential and commercial lots. Developers expect it to take about three years, with construction set to begin in December.
The full project could take 20 to 30 years and more than 10 phases. Spread evenly, 3,000 units over that span works out to roughly 100 to 150 a year. Clore Station will change what kind of home you can buy in Crestwood long before it changes how many homes are for sale. Phase one is mostly a new set of home types and price points. The overall pace is set by Oldham County's review process and by road work that runs on its own schedule.
Phase one brings home types Crestwood hasn't offered at this scale
Clore Station's published phase one plan lists single-family homes, mews homes, "mansion apartments," townhomes, live/work units and mixed-use commercial space. The plan describes each format, and in July, WLKY reported the expected starting prices.
| Home type | Format per the plan | Expected starting price, per WLKY |
|---|---|---|
| Mansion apartments | 2 to 3 story condo buildings, 4 to 8 units each, variable unit sizes | About $350,000 |
| Townhomes | Two stories, 1,600 to 2,800 sq ft | About $550,000 |
| Mews | Three stories, 1,300 to 2,400 sq ft | No price reported |
| Single-family | Two stories, 1,500 to 4,000 sq ft, two lot-size options | About $800,000 |
Compare that with new construction already selling nearby. Royal Oaks, at 6635 Gibson Way in Crestwood, is marketed by its builder with single-family plans starting at $523,900. Oldham County recorded a 67-lot plat for Royal Oaks Section 3 on August 21.
At the high end, Clore Station's detached homes start well above Royal Oaks, so they won't compete head-to-head with that existing subdivision. The new part is the low end of the ladder. A $350,000 condo or a $550,000 townhome in a walkable, mixed-use plan has not been an option in Crestwood new construction until now. The planning firm is DPZ, which also designed Norton Commons. Clay Jones of Clore Station Development told WLKY the project will follow "the same style of development in a walkable, mixed-use, urban-style neighborhood" without copying Norton Commons outright.
You won't be choosing among one or two builders. The Clore Station builders guild names Bailey Homes, Bentley Homes, Caliber Homes, Deville Homes, Eldridge Company, Joe Kroll Builder, Key Homes, Mason Construction & Development, Orthober Homes, Ramage Company, Stonehenge Construction, The Jones Group, TJM Custom Homes, Tracee Dore Builders and WinMark. The roster does not say which builder will build which lots. Jones told WLKY the team had "a list of probably 300 different entities" it was contacting to match with builders.
The county review process sets the pace
The product mix matters more than the headline count because each phase of Clore Station has to clear county review on its own. When the Oldham County Planning Commission approved the zoning, master plan and form-based code 11-0, the Oldham Era reported that each phase will go back to the Technical Review Committee. Clore Station's attorney said each phase will come with a new traffic study, and the developer will handle any road improvements attributed to it.
The next steps are already in that process. At its April 15, 2026 meeting, the Technical Review Committee took up Clore Station Sections 2 and 3 at 6530 Dovefield Drive, 581 dwelling units in total. The project engineer described them this way:
- Phase two: 34 acres, 326 dwelling units, 3.82 acres of open space, a community building, and sewers throughout.
- Phase three: 37 acres, 255 units, 2.01 acres of open space.
- Both: multiple detention basins and a new traffic impact study.
The same minutes say "phase one is currently under construction," and in July WLKY called phase one "well underway." The October coverage gives December as the start of construction. The coverage doesn't explain the gap between those accounts. If you're thinking about a presale, ask the builder what has actually started on your lot and which milestone your closing date depends on.
Countywide numbers show how small Crestwood's new-home pipeline has been. Oldham County's August 2026 planning report shows 138 new subdivision lots recorded across the whole county from January through August, with 67 of them recorded in August. A 581-unit section plan is larger than four years of lots at that pace. That explains why Clore Station's later sections are moving through review in pieces, each with its own traffic study.
Rules for other projects are tight too. In July, the Planning Commission voted 10-2 to recommend denying an 84-unit apartment proposal at Highway 22 and Clore Lane, after more than 15 residents spoke against it, according to the Oldham Era. The Fiscal Court has the final say. Even if the project were approved, the applicant said it would be limited to building 75 units a year. New homes in Crestwood are released a little at a time.
The road projects will take even longer
The intersection that came up most at that hearing is a good example of the timing. The Kentucky Transportation Cabinet plans to realign Clore Lane with Wooldridge Avenue and widen Highway 22 with left-turn lanes. Here is where that project and two other Crestwood corridor projects stand.
- Clore Lane and Highway 22: at the July hearing, the county engineer said construction is "scheduled for 2028," with completion probably in 2029 "if this keeps going."
- KY 22 and KY 146 in downtown Crestwood: KYTC's project page for the junction and its railroad crossing shows preliminary design as of summer 2026, final design possibly starting in 2026, right-of-way and utility work possibly in 2029, and construction possibly starting in 2030. All dates are subject to change.
- I-71 widening from KY 329 to KY 393: KYTC's page shows four lanes becoming six, with roadway construction starting in 2027 or 2028 based on a schedule from summer 2025. No completion date is listed.
Clore Station's three-year first phase is expected to wrap up around the time construction is just getting started at Clore Lane, and before it starts at all at the KY 22 and KY 146 junction. Anyone buying in the early sections will also be living next to construction on the later ones. Phase one buyers are getting in early on a 20- to 30-year build, and that is part of what they're paying for.
A presale is competing with a looser resale market
The fair comparison for a Clore Station presale is what's for sale today. The Greater Louisville Association of REALTORS' August 2026 report shows a regional market that gave buyers more room than a year earlier:
- 4,490 homes for sale, up 33% year over year
- 3.5 months of inventory, up from 2.7
- 1,054 pending sales, down 26.3%
- 46 cumulative days on market, compared with 38 in August 2025
- A $300,000 median sale price, up 1.2%, with sellers receiving an average of 98.6% of list price
Those are regional figures, not Crestwood figures. Still, they describe the market a phase one buyer is giving up. An existing home can be inspected and closed now, in a regional market with more listings and slower sales than a year ago. A Clore Station home offers a mix of product and walkability that no resale in Crestwood offers, but you'll get it later, on a schedule set by county review and builder timelines. For many buyers it makes sense to price out both options side by side before signing a presale contract.
Common Questions
Is the hospital part of the first phase? Baptist Health's hospital campus near Exit 14 and KY 329 has been part of the Clore Station plan since the master plan was approved. The October coverage still lists a hospital among the project's planned components but gives no construction or opening date. The next two phases, which include more housing, businesses and senior living, are still being designed.
How big could Clore Station make Crestwood? Jones told WLKY the project could bring "another 5,000, 6,000, 7,000 or 8,000 people" over 20 to 30 years, which he said would probably double the city's population over that time.
What else is planned besides homes? WDRB and WAVE reported a 50,000-square-foot arts center for visual arts, music, dance and drama. It will sit on land the developers donated after the Oldham County Arts Center expressed interest in joining the project.
Deciding between a Clore Station presale and a Crestwood home you can move into this year? Or wondering what a new walkable neighborhood near Exit 14 could mean for the house you already own? Sam Stone can lay out today's Crestwood comps next to the phase one price ladder so you can see the tradeoff in real numbers. If you're selling, start with an Instant Home Valuation.